The Alpine Power Plant is really taking shape now that all major equipment has arrived and been sat on their foundations. Project Manager Brian Bejcek has provided the latest progress at Alpine:
The turbines and generators for Units 1 and 2 are now sat on their foundations and are being rough aligned.
Both GSU transformers have been sat on their foundations.
The air-cooled heat exchanges are currently being erected.
The crew will be wrapping up the last of the underground construction over the next few weeks.
TransCanada is wrapping up their work of connecting Alpine to the existing natural gas pipeline and should be finished by mid-January.